ACN Offshore has successfully completed supporting Saipem in the decommissioning of the BP Miller platform. ACN safely managed and executed Scaffolding, Rope Access, Welding, Cutting, Rigging and NDT Inspection.

The platform is one of the largest platforms to be decommissioned to date in the North Sea, the Topside equalling 28,700 tonnes. This being approximately 366 times larger than the NUI Horne & Wren platform ACN decommissioned in 2016.

Working in a challenging environment approximately 150 miles from land out into the Central North Sea, ACN is pleased to report that from nearly 50,000 manhours executed there were no accidents during the project and safety remained paramount.